Construction Schedule and Phasing
The following phasing information reflects initial plans for construction scheduling. Changes to the schedule and construction phasing activities may occur.
Segment 1: Southbound I-15 from I-215 interchange to Silverado Ranch

Segment 1 Activities
- Construction of the southbound auxiliary lane between Blue Diamond Road and Silverado Ranch Boulevard
- Reconstruction of ramps at the Blue Diamond Road interchange
- Construction of the southbound collector-distributor roads
- Connecting I-215 ramps to the southbound collector-distributor roads
Phase |
Segment 1 Major Work Elements |
Approx Duration |
1A |
Auxiliary lane south of Blue Diamond |
15 weeks |
1B |
Collector-Distributor roads at Blue Diamond & temporary paving for future eastbound Blue Diamond |
4 weeks |
1C |
I-15 ramp to westbound Blue Diamond. Collector-Distributor road from Blue Diamond to south of Warm Springs |
6 months |
1D |
Temporary ramp pavement I-215 westbound ramp to I-15 southbound & bridge construction over I-215 mainline and I-215 eastbound off-ramp to Las Vegas Blvd, I-15 southbound to I-215 eastbound ramp. |
9 months |
2A |
Collector-Distributor bridge work at Blue Diamond Interchange and associated ramp work |
12 months |
2B |
I-215 eastbound ramp to collector-distributor south of Warm Springs |
4 months |
2C |
I-215 westbound ramp to southbound collector-distributor |
6 weeks |
3A |
Complete collector-distributor at Blue Diamond & ramp work |
4 weeks |
3B |
Complete collector-distributor at I-15 & I-215 eastbound |
2 weeks |
An early action item in Segment 1 will be the southbound auxiliary lane between Blue Diamond and Silverado Ranch. During construction, I-15 traffic will remain in its existing lane configuration with a reduced right shoulder.
The overall duration of work activities in Segment 1 is expected to be approximately 26 months.
Segment 2: Southbound I-15 from Tropicana Avenue to I-215

Segment 2 Activities
- Construction of southbound C-D roads from Tropicana Avenue to I-215
- Ramp improvements at Russell Road, Tropicana Avenue, and I-215 southbound ramps
- Affiliated work such as bridges at I-215, Russell Road and the Tropicana Wash Lid (concrete covering over the Tropicana Wash)
| Phase | Segment 2 Major Work Elements |
Approx Duration |
1A |
Bridge construction for median widening on I-15 at I-215; bridge widening for the collector-distributor roads at I-215; mainline I-15 widening from Warm Springs to I-215 |
6 months |
1B |
I-15 to I-215 eastbound and westbound ramp improvements |
11weeks |
1C |
Collector-distributor from I-215 to UPRR; improvements on Dean Martin |
19 weeks |
1D |
Bridge construction associated with ramp widening for I-15 to I-215 eastbound |
9 months |
1E |
Collector-distributor from UPRR to Russell on-ramp |
17 weeks |
1F |
Collector-Distributor at Russell & Russell bridge improvements |
9 months |
1G |
Tropicana Wash Lid and associated collector-distributor; Tropicana on-ramp improvements |
12 months |
2A |
Improvements to the I-15 to I-215 westbound ramp |
36 weeks |
2B |
Russell on-ramp widening; collector-distributor in the vicinity of the on ramp gore |
7 weeks |
2C |
Russell off-ramp widening; Collector-distributor in the vicinity of the off-ramp gore |
10 weeks |
2D |
Complete Tropicana ramp over the Tropicana Wash Lid |
7 weeks |
3A |
I-15 to I-215 eastbound ramp improvements, Collector-distributor bridge construction over the I-15 to I-215 ramp |
10 months |
3B |
Complete collector-distributor tie-in at Warm Springs and the eastbound I-215 to I-15 ramp |
6 weeks |
The overall duration of work activities in Segment 2 is expected to be approximately 21 months.
Segment 3: Northbound I-15 from Tropicana Avenue to I-215

Segment 3 Activities
- Construction of the northbound C-D roads from I-215 to Tropicana Avenue
- Ramp improvements at I-215, Russell Road and Tropicana Avenue
- Affiliated work such as bridges at I-215 and Russell Road
Phase |
Phase 3 Major Work Elements |
Approx Duration |
1A |
Bridge widening over I-215 eastbound off-ramp to Las Vegas Blvd, and I-15 southbound to I-215 eastbound ramp. Northbound median widening on I-15 at I-215 including bridge work |
6 months |
1B |
Collector-distributor roads from I-215 to UPRR. Bridge construction over I-215 mainline, and over northbound I-15 to westbound I-215 as well as over westbound I-215 to northbound I-15 on-ramp |
12 months |
1C |
Collector-distributor roads at Russell Rd. Collector-distributor bridge construction at Russell & Russell bridge widening |
18 months |
1D |
Collector-distributor road from Russell to Tropicana. West half of Tropicana off-ramp |
14weeks |
1E |
Ramp improvement I-215 westbound to I-15 northbound |
6 weeks |
2A |
Complete ramp improvement 1-215 westbound to I-15 northbound |
8 weeks |
2B |
Collector-distributor from UPRR to Russell ramps |
12 weeks |
2C |
Construct the east half of the Russell on-ramp |
10 weeks |
2D |
Construct west half of the Tropicana off-ramp |
12 weeks |
2E |
Complete ramp improvements I-215 westbound to I -15 northbound |
6 weeks |
3A |
Complete collector-distributor at I-215 |
4 weeks |
3B |
Complete collector-distributor south of Russell & complete the west half of the Russell off-ramp |
12 weeks |
The overall duration of work activities in Segment 3 is expected to be 18 months.
Segment 4: Northbound I-15 from I-215 interchange to Silverado Ranch
Segment 4 Activities
- Construction of the northbound collector-distributor roads from Blue Diamond Road to I-215
- Reconstruction of ramps at the Blue Diamond Road interchange
- Connecting I-215 ramps to the new collector-distributor roads
Phase |
Major Work Elements |
Approx Duration |
1A |
Auxiliary lane from Silverado Ranch to Blue Diamond; east half of the Blue Diamond off-ramp |
12 months |
1B |
Construct portion of the collector-distributor road at Blue Diamond |
5 weeks |
1C |
Construct Blue Diamond flyover bridge and approaches; construct collector-distributor Blue diamond to Warm Springs |
4 months |
1D |
Collector-distributor road from Warm Springs to I-215, portions of the I-215 off-ramp eastbound and westbound |
15 weeks |
2A |
West half of the Blue Diamond off-ramp; collector-distributor infill work between phase 1A and 1B |
7 weeks |
2B |
Bridge work on Blue Diamond flyover connection to the collector-distributor road |
12 months |
2C |
Mainline widening from Blue Diamond to I-215 |
16 weeks |
2D |
Remaining portions of the collector-distributor at Warm Springs |
9 weeks |
3A |
Complete mainline widening |
15 weeks |
3B |
Complete work on the I-215 on-ramps |
13 weeks |
The overall duration of work activities in Segment 4 is expected to be 20 months.
Sunset Road Bridge
The newly constructed Sunset Road Bridge will span over I-15. Construction is expected to take approximately nine months. No detour or closure is expected for Sunset Road since no crossing currently exists.
Warm Springs Road Bridge
Warm Springs Road is an existing bridge spanning over I-15. As part of the scope of work, the existing bridge will be removed and a new bridge constructed. During the time that Warm Springs Road is closed for construction, traffic will be detoured.
UPRR Bridge
The existing Boulder Branch UPRR bridge will be left in place and new end spans will be constructed, eliminating the need for major impacts to I-15 traffic. The end spans will be constructed during UPRR closure periods and over the new collector-distributor roads, away from mainline traffic. Shoulder reductions and closures will be needed.