Construction Schedule and Phasing

The following phasing information reflects initial plans for construction scheduling. Changes to the schedule and construction phasing activities may occur.

Segment 1: Southbound I-15 from I-215 interchange to Silverado Ranch

MOT_Phase_1 H.png

Segment 1 Activities

  • Construction of the southbound auxiliary lane between Blue Diamond Road and Silverado Ranch Boulevard
  • Reconstruction of ramps at the Blue Diamond Road interchange
  • Construction of the southbound collector-distributor roads
  • Connecting I-215 ramps to the southbound collector-distributor roads

Phase

Segment 1 Major Work Elements

Approx Duration

1A

Auxiliary lane south of Blue Diamond

15 weeks

1B

Collector-Distributor roads at Blue Diamond & temporary paving for future eastbound Blue Diamond

4 weeks

1C

I-15 ramp to westbound Blue Diamond.  Collector-Distributor road from Blue Diamond to south of Warm Springs

6 months

1D

Temporary ramp pavement I-215 westbound ramp to I-15 southbound & bridge construction over I-215 mainline and I-215 eastbound off-ramp to Las Vegas Blvd, I-15 southbound to I-215 eastbound ramp.

9 months

2A

Collector-Distributor bridge work at Blue Diamond Interchange and associated ramp work

12 months

2B

I-215 eastbound ramp to collector-distributor south of Warm Springs

4 months

2C

I-215 westbound ramp to southbound collector-distributor

6 weeks

3A

Complete collector-distributor at Blue Diamond & ramp work

4 weeks

3B

Complete collector-distributor at I-15 & I-215 eastbound

2 weeks

An early action item in Segment 1 will be the southbound auxiliary lane between Blue Diamond and Silverado Ranch. During construction, I-15 traffic will remain in its existing lane configuration with a reduced right shoulder.   
The overall duration of work activities in Segment 1 is expected to be approximately 26 months.

Segment 2: Southbound I-15 from Tropicana Avenue to I-215

MOT_Phase_2 H.png

Segment 2 Activities

  • Construction of southbound C-D roads from Tropicana Avenue to I-215
  • Ramp improvements at Russell Road, Tropicana Avenue, and I-215 southbound ramps
  • Affiliated work such as bridges at I-215, Russell Road and the Tropicana Wash Lid (concrete covering over the Tropicana Wash)
Phase

Segment 2 Major Work Elements

Approx Duration

1A

Bridge construction for median widening on I-15 at I-215; bridge widening for the collector-distributor roads at I-215; mainline I-15 widening from Warm Springs to I-215

6 months

1B

I-15 to I-215 eastbound and westbound ramp improvements

11weeks

1C

Collector-distributor from I-215 to UPRR; improvements on Dean Martin

19 weeks

1D

Bridge construction associated with ramp widening for I-15 to I-215 eastbound

9 months

1E

Collector-distributor from UPRR to Russell on-ramp

17 weeks

1F

Collector-Distributor at Russell & Russell bridge improvements

9 months

1G

Tropicana Wash Lid and associated collector-distributor; Tropicana on-ramp improvements

12 months

2A

Improvements to the I-15 to I-215 westbound ramp

36 weeks

2B

Russell on-ramp widening; collector-distributor in the vicinity of the on ramp gore

7 weeks

2C

Russell off-ramp widening; Collector-distributor in the vicinity of the off-ramp gore

10 weeks

2D

Complete Tropicana ramp over the Tropicana Wash Lid

7 weeks

3A

I-15 to I-215 eastbound ramp improvements, Collector-distributor bridge construction over the I-15 to I-215 ramp

10 months

3B

Complete collector-distributor tie-in at Warm Springs and the eastbound I-215 to I-15 ramp

6 weeks

The overall duration of work activities in Segment 2 is expected to be approximately 21 months.

Segment 3: Northbound I-15 from Tropicana Avenue to I-215

MOT_Phase_3 H.png

Segment 3 Activities

  • Construction of the northbound C-D roads from I-215 to Tropicana Avenue
  • Ramp improvements at I-215, Russell Road and Tropicana Avenue
  • Affiliated work such as bridges at I-215 and Russell Road

Phase

Phase 3 Major Work Elements

Approx Duration

1A

Bridge widening over I-215 eastbound off-ramp to Las Vegas Blvd, and I-15 southbound to I-215 eastbound ramp. Northbound median widening on I-15 at I-215 including bridge work

6 months

1B

Collector-distributor roads from I-215 to UPRR.  Bridge construction over I-215 mainline, and over northbound I-15 to westbound I-215 as well as over westbound I-215 to northbound I-15 on-ramp

12 months

1C

Collector-distributor roads at Russell Rd.  Collector-distributor bridge construction at Russell & Russell bridge widening

18 months

1D

Collector-distributor road from Russell to Tropicana.  West half of Tropicana off-ramp

14weeks

1E

Ramp improvement I-215 westbound to I-15 northbound

6 weeks

2A

Complete ramp improvement 1-215 westbound to I-15 northbound

8 weeks

2B

Collector-distributor from UPRR to Russell ramps

12 weeks

2C

Construct the east half of the Russell on-ramp

10 weeks

2D

Construct west half of the Tropicana off-ramp

12 weeks

2E

Complete ramp improvements I-215 westbound to I -15 northbound

6 weeks

3A

Complete collector-distributor at I-215

4 weeks

3B

Complete collector-distributor south of Russell & complete the west half of the Russell off-ramp

12 weeks

The overall duration of work activities in Segment 3 is expected to be 18 months.

Segment 4: Northbound I-15 from I-215 interchange to Silverado Ranch

MOT_Phase_4 H.png

Segment 4 Activities

  • Construction of the northbound collector-distributor roads from Blue Diamond Road to I-215
  • Reconstruction of ramps at the Blue Diamond Road interchange
  • Connecting I-215 ramps to the new collector-distributor roads 

Phase

Major Work Elements

Approx Duration

1A

Auxiliary lane from Silverado Ranch to Blue Diamond;  east half of the Blue Diamond off-ramp

12 months

1B

Construct portion of the collector-distributor road at Blue Diamond

5 weeks

1C

Construct Blue Diamond flyover bridge and approaches; construct collector-distributor Blue diamond to Warm Springs

4 months

1D

Collector-distributor road from Warm Springs to I-215, portions of the I-215 off-ramp eastbound and westbound

15 weeks

2A

West half of the Blue Diamond off-ramp; collector-distributor infill work between phase 1A and 1B

7 weeks

2B

Bridge work on Blue Diamond flyover connection to the collector-distributor road

12 months

2C

Mainline widening from Blue Diamond to I-215

16 weeks

2D

Remaining portions of the collector-distributor at Warm Springs

9 weeks

3A

Complete mainline widening

15 weeks

3B

Complete work on the I-215 on-ramps

13 weeks

The overall duration of work activities in Segment 4 is expected to be 20 months.

Sunset Road Bridge
The newly constructed Sunset Road Bridge will span over I-15. Construction is expected to take approximately nine months. No detour or closure is expected for Sunset Road since no crossing currently exists.

Warm Springs Road Bridge
Warm Springs Road is an existing bridge spanning over I-15. As part of the scope of work, the existing bridge will be removed and a new bridge constructed. During the time that Warm Springs Road is closed for construction, traffic will be detoured.

UPRR Bridge
The existing Boulder Branch UPRR bridge will be left in place and new end spans will be constructed, eliminating the need for major impacts to I-15 traffic. The end spans will be constructed during UPRR closure periods and over the new collector-distributor roads, away from mainline traffic. Shoulder reductions and closures will be needed.

 Traffic Alerts
 
 Announcements
 Polls
 Diversity Program
* Click here for information about I-15 Design-Build South’s Disadvantaged Business Enterprise Program.
Name (required)
Company Name
Telephone (required)
Email (required)
Inquiry Details (required)